  • The contractor has converted a record preconstruction pipeline into main contracts and is putting defence and healthcare at the centre of its growth plan.
  • Willmott Dixon secured £747m of new work by the end of July, 89% of it under main contract, and reported pre-tax profit up 15% to £11.5m for the six months to June. The contractor is targeting a £1.5bn construction business, with defence and healthcare leading expansion even as cost pressures squeeze customers and suppliers.
Conceptual illustration of tower cranes above a partly built urban block, with site plans and building materials in the foreground.

Willmott Dixon is aiming to build a £1.5bn construction business, setting out growth ambitions after securing nearly £750m of new work in the first half of the year and turning a record level of preconstruction appointments into main contracts.

The contractor said defence and healthcare would spearhead the expansion, with its construction division targeting growth from turnover of £1.03bn last year. Revenue growth is expected to build from 2027.

Chief executive Graham Dundas said the priority for the year had been converting preconstruction appointments into main contracts. By the end of July the group had secured £747m of new work, 89% of it under main contract, which he said gives secure and visible revenue for 2027 and beyond.

Profit rises as revenue edges lower

Group pre-tax profit climbed 15% to £11.5m in the six months to June, even as revenue edged down to £545m from £548m, a movement the company linked to major starts taking time to come through.

Willmott Dixon now holds a £1.37bn secured order book and more than £3.5bn of identified workload, taking its total pipeline to around £5bn.

The company's focus on conversion reflects the gap between work won and revenue recognised: the £747m secured by the end of July sits largely outside the £545m booked in the six months to June, with much of the newly signed work due to feed through from 2027.

Education leads the project wins

Education delivered the largest contract awards, led by the £93m College of North West London campus at Wembley and the £58m Mosslands secondary school. Further work includes £28m of affordable homes at Princes Gate in Oldham for Muse, Portsmouth's £22m Bransbury Park Leisure Centre and the £16m Bath Fire Station.

Frameworks remain the main engine of orders, generating around 90% of new work, according to the company.

Balance sheet strengthened

The group also strengthened its cash position to £127m, with no debt and record shareholders' funds of £190m.

Cost pressures persist

Dundas warned that cost pressures were still squeezing customers and suppliers. Global conflicts continue to push up energy, fuel and material costs, he said, and both customers and supply chain partners are feeling the pressure. When customers choose who to work with, financial resilience and a proven delivery record matter more than ever.

Developments arm seeks regeneration work

The relaunched Willmott Dixon Developments arm is also hunting growth through public sector regeneration partnerships, most recently securing the £100m Baytree Shopping Centre scheme in Brentwood with Milligan.

With a pipeline of around £5bn and a debt-free balance sheet, the group is positioning itself for expansion even as cost inflation continues to weigh on the wider supply chain.

Reported by Maren Kjellberg, Concrete and Asphalt Machinery Editor.