TriMark Executive Outlines Equipment Rollout Playbook for Menu Launches

Katarina VukovicNovember 1, 20265 min read1 views

At a glance

  • A TriMark USA national-accounts executive says location audits, lead-time schedules and consolidated packaging can reduce friction when new menu items require new equipment.
  • Bryan Musgrove of TriMark USA recommends building a location-specific playbook, scheduling equipment deliveries around manufacturer lead times, and consolidating smallwares into one package per site. He cites toaster and macaroni-and-cheese rollouts to show how electrical, space and delivery constraints can shape a menu launch.
A conceptual cutaway of commercial kitchen bays and a delivery area shows toasters, pans, shelving and consolidated cartons used to plan an equipment rollout across restaurant locations.

Rolling out a new menu item involves more than recipe development and marketing. For multi-unit restaurant brands, the equipment needed at each location can determine whether a launch stays on schedule. Bryan Musgrove, divisional senior director on national accounts for TriMark USA, has worked on several equipment rollouts tied to menu additions and shared practices aimed at making those projects more predictable.

His first recommendation is to create a rollout playbook that treats locations individually rather than assuming a single installation plan fits every site. A brand that wanted to add toasted sandwiches to a breakfast lineup already featuring biscuits and wraps needed new toasters. Some restaurants could accommodate the equipment without major changes, but others had constraints. Electrical capacity was already fully used at some sites, while a small mall or urban restaurant lacked the counter space for a toaster. In those cases, the operator might need to add shelving or another table, a change that can affect workflow. The playbook should separate locations that can accept the equipment as-is from those requiring extra work.

Schedule around manufacturing lead times

Musgrove also advises building the installation schedule from the equipment manufacturer’s actual lead time. A supplier may be able to produce 200 units, but the relevant question is how long production will take. At a rate of 10 units per week, that order would require 20 weeks. A manufacturer might also have inventory for the first 50 units, then need to wait eight weeks for parts sourced overseas before completing the remainder. For a menu item tied to a seasonal or occasion-based marketing campaign, the brand should begin with the target launch date and work backward to establish a timeline that reflects those production realities.

Consolidate deliveries by location

The third practice concerns packaging and delivery. Smallwares can be shipped directly to restaurants in their original boxes, but Musgrove suggests asking the dealer to consolidate and repackage them into one package for each location. TriMark worked with a brand that added macaroni and cheese to its side-item lineup. The addition required visual holding cabinets, pans and serving scoops in several sizes. The items were combined into a single package per location, along with instructional materials and exterior labeling. That gave managers a clear view of what each delivery contained when it arrived.

Together, the steps address two parts of an equipment rollout that can create friction: deciding which locations need more support and making deliveries easier to manage. Musgrove presents them as a way to help ensure a smoother rollout. If the launch goes as planned, the new menu item may generate attention and increase traffic.

Reported by Katarina Vukovic, Laser Cutting & Source Specialist.